Serving the Oil & Gas Industry Since 1980

 

 Yucatan Peninsula Gas Pipeline Project

 

In mid July, 1995 Fluor Daniel Williams Brothers of Houston, Texas awarded EN-FAB, Inc. a purchase order to engineer and fabricate ancillary equipment required for a 340 km, 20" pipeline project for Colombia, the Mariquita to Cali gas pipeline.

 

Through an aligned relationship to review and approve all design issues, Fluor Daniel Williams Brothers and EN-FAB have managed to meet a demanding execution schedule. All one hundred and eight (108) skids had to be completed within a short eight (8) months delivery schedule.

 

The demanding eight month delivery schedule was accomplished by Fluor Daniel Williams Brothers and En-Feb using the latest technology to engineer, design, approve, build, and test the equipment. The packages were engineered to allow standardization. The philosophy of the design was, use common arrangements of the equipment to facilitate drawing preparation and fabrication. Drawing transmittal was achieved using a computer MODEM link between Fluor Daniel Williams Brothers and EN-FAB in Houston, and Fluor Daniel Williams Brothers and its project office in Colombia.

 

Equipment provided:

20" Pipeline Gas Inlet Station at Mariquita

20" Main Line Launchers and Receivers

Main Line Block Stations

Lateral Launcher Stations 2" thru 8"

City Gate Stations 0.5 MMSCFD to 77 MMSCFD of natural gas

Solar Panels to power the remote stations SCADA equipment

Remote Transmission Units used to collect and send information

Indirect Fired Gas Heaters

Electric Heaters

Filter Separators

Odorizer Stations

 

Previous Project

Next Project

Mariqita-Cali Gas Pipeline Project

Location: Columbia

Gas Gathering

Contact Info

EN-FAB, Inc.

3905 Jensen Drive

Houston, Texas 77026

Mon - Fri 08:00 - 17:00

Metering  Measurement

As of August 2017, the Mariquita – Cali gas pipeline, and its segments, has a total length of 740 km, and supplies natural gas to 48 municipalities located in the departments of Tolima, Caldas, Risaralda, Quindío and Valle del Cauca. The main line of the gas pipeline is 20-inch width and has 66 connection points for local providers and thermal power plants located in the area.

EN-FAB, Inc. Recent Posts

NIPER-580 recognized EN-FAB, Inc. as the only company to provide . . . . .

EN-FAB completes acquisition of  Oman Metal Industries & Contracting LLC  . . . . .

Subscribe to our Newsletter

Keep up with our latest projects by  subscribing to our newsletter

Submitting Form...

The server encountered an error.

Form received.

CALL US NOW

 

Office: +1 713 225 4913

Fax:       +1 713 224 7937